Vehicle Administration Centre’s PALKO information system project
The presentation of the project’s cost estimates in the state
budget has in many respects been incomplete and unclear. The audit sought to determine whether the planning of the PALKO project and subprojects has been precise and properly weighted. It also
sought to determine whether the project and subprojects have remained
under control and what reasons have led to any gaps in control. This document contains a summary of the main results of the audit. The entire audit report is available only in Finnish.